Article Summary: The West African College of Surgeons is building a new permanent secretariat on Harvey Road, Yaba. The 6-floor development began construction in 2015 with a planned completion date of Q4:2017. Initially designed to include a museum, conference hall, offices, library and computer room, committee rooms, the project has undergone updates, but its core purpose remains the College's new central hub.
- Name: Permanent Secretariat Building for West African College of Surgeons;
- Address: 4 Harvey Road, Off Herbert Macaulay Way, Yaba – Lagos;
- Project Manager: Architects Group Practice;
- Architect: Q Design Consultants;
- Structural Engineer: Multiplan Consultants;
- Mechanical Engineer: Consem Associates;
- Electrical Engineer: Niyex Consulting Engineers;
- Quantity Surveyor: BQC Consultants Limited;
- Contractor: Telisol Limited.
This 6 floor development located on Harvey Road in Yaba is being developed by the West African College of Surgeons to act as their new permanent secretariat. The West African College of Surgeons, whose objectives include promoting, organising and conducting postgraduate education and training in surgery within West Africa, are currently located in another property on Taylor Drive, Yaba.
When the College began to outgrow their office in 2012, they acquired the site for this development. A pre-qualification process to select the building contractor began in 2014 and construction started shortly afterwards during 2015.
Initial plans for the property included a historical museum & bookshop on the ground floor, a Conference hall with a 250 man hall on the 1st floor, office spaces on the 2nd – 4th floors, library and computer room on the 5th floor and a committee room on the 6th and topmost floor.
Based on the current pace of construction, the development may be completed during Q4:2017.




Related News
You will find these interesting

Chidubem Nwaonicha-Emegha . May 2026
Impact of the USA/Iran War on Nigeria’s Real Estate
construction
Iran/USA War

Chidubem Nwaonicha-Emegha . October 2025
The Nigerian Tax Act 2025: Implications For The Real Estate Sector
mortgage
nigeria

Dapo Runsewe . February 2025
Tetra Pak West Africa Relocates HQ to The Phoenix in Ikeja
africa
development